Niemiec
Corporation keeps careful track of the time required to fill orders. The times
recorded for a particular order appear below:
Hours
Move time ……….. 2.6
Wait time ………… 13.3
Queue time ………… 8.5
Process time ……….. 1.5
Inspection time ………. 0.2
The manufacturing cycle efficiency (MCE) was closest to:
0.96
0.12
0.06
0.20